In the Gantt component, you can change the schedule start and end dates by clicking the custom button programmatically using the updateProjectDates
method. You can pass the start and end dates as method arguments to the updateProjectDates
method. You can also pass the Boolean value as an additional parameter, which is used to round-off the schedule start and end dates displayed in Gantt timeline.
import { NgModule } from '@angular/core'
import { BrowserModule } from '@angular/platform-browser'
import { GanttModule } from '@syncfusion/ej2-angular-gantt'
import { Component, ViewEncapsulation, OnInit, ViewChild } from '@angular/core';
import { Gantt } from '@syncfusion/ej2-gantt';
import { GanttComponent } from '@syncfusion/ej2-angular-gantt';
import { ButtonComponent } from '@syncfusion/ej2-angular-buttons';
import { editingData } from './data';
@Component({
imports: [
GanttModule
],
standalone: true,
selector: 'app-root',
template:
`<button ejs-button id='changedate' (click)='change()'>Change Date</button>
<br><br>
<ejs-gantt #gantt id="ganttDefault" height="430px" [dataSource]="data" [taskFields]="taskSettings"></ejs-gantt>`,
encapsulation: ViewEncapsulation.None
})
export class AppComponent{
// Data for Gantt
public data?: object[];
public taskSettings?: object;
@ViewChild('gantt', {static: true})
public ganttObj?: GanttComponent;
public ngOnInit(): void {
this.data = editingData;
this.taskSettings = {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
duration: 'Duration',
progress: 'Progress',
parentID:'ParentID',
};
}
change(): void {
this.ganttObj!.updateProjectDates(new Date('04/10/2019'),new Date('06/20/2019'),true);
};
}
import { bootstrapApplication } from '@angular/platform-browser';
import { AppComponent } from './app.component';
import 'zone.js';
bootstrapApplication(AppComponent).catch((err) => console.error(err));