Getting Started with the Vue Gantt Chart Component in Vue 2

5 Mar 202624 minutes to read

This article provides a step-by-step guide for setting up a Vue 2 project using Vue-CLI and integrating the Syncfusion® Vue Gantt Chart component.

To get started quickly with Vue Gantt Chart, check this video:

Prerequisites

System requirements for Syncfusion® Vue UI components

Dependencies

Following is the list of dependencies to use the Gantt with all features:

|-- @syncfusion/ej2-gantt
    |-- @syncfusion/ej2-base
    |-- @syncfusion/ej2-buttons
    |-- @syncfusion/ej2-calendars
    |-- @syncfusion/ej2-data
    |-- @syncfusion/ej2-dropdowns
    |-- @syncfusion/ej2-grids
    |-- @syncfusion/ej2-inputs
    |-- @syncfusion/ej2-layouts
    |-- @syncfusion/ej2-lists
    |-- @syncfusion/ej2-navigations
    |-- @syncfusion/ej2-popups
    |-- @syncfusion/ej2-richtexteditor
    |-- @syncfusion/ej2-treegrid

Setup the Vue 2 project

To generate a Vue 2 project using Vue-CLI, use the vue create command. Follow these steps to install Vue CLI and create a new project:

npm install -g @vue/cli
vue create quickstart
cd quickstart
npm run serve

or

yarn global add @vue/cli
vue create quickstart
cd quickstart
yarn run serve

When creating a new project, choose the option Default ([Vue 2] babel, eslint) from the menu.

Vue 2 project

Once the quickstart project is set up with default settings, proceed to add Syncfusion® components to the project.

Add Syncfusion® Vue packages

Syncfusion® packages are available at npmjs.com. To use Vue components, install the required npm package.

This article uses the Vue Gantt Chart component as an example. Install the @syncfusion/ej2-vue-gantt package by running the following command:

npm install @syncfusion/ej2-vue-gantt --save

or

yarn add @syncfusion/ej2-vue-gantt

Import Syncfusion® CSS styles

Syncfusion® components require CSS stylesheets to display correctly. You can import themes in various ways, such as using CSS or SASS styles from npm packages, CDN, CRG, and Theme Studio. Refer to themes topic to learn more about built-in themes and different ways to reference themes in a Vue project.

In this article, the Tailwind3 theme is applied using CSS styles, which are available in installed packages. The necessary Tailwind3 CSS styles for the Gantt Chart component and its dependents were imported into the <style> section of the src/App.vue file.

<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
 @import '../node_modules/@syncfusion/ej2-notifications/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Important The order of CSS imports matters. Import base styles first, then component-specific styles. Missing CSS imports can result in misaligned layouts, buttons without styling, or missing visual elements in popups and dialogs.

Add Syncfusion® Vue component

Follow the below steps to add the Vue Gantt Chart component:

1. First, import and register the Gantt Chart component in the script section of the src/App.vue file.

<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
export default {
  components: {
    'ejs-gantt': GanttComponent
  }
}
</script>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";

export default {
name: "App",
components: {
"ejs-gantt':":Gantt':Component
}
}
</script>

2. In the template section, define the Gantt Chart component.

<template>
    <div id="app">
    <ejs-gantt></ejs-gantt>
  </div>
</template>

Register the Syncfusion® Vue component

A Syncfusion® Vue component needs to be registered so that Vue knows where to locate its implementation when it is encountered in a template.

To use directives like e-columns and e-column for defining Gantt columns, import the Gantt Chart component along with the required child directives from the installed packages into the <script> section of the src/App.vue file. Register the Gantt Chart component along with the required child directives using the following code:

<script setup>
   import { GanttComponent as EjsGantt, ColumnsDirective as EColumns, ColumnDirective as EColumn } from '@syncfusion/ej2-vue-gantt';
</script>
<script>
    import { GanttComponent, ColumnsDirective, ColumnDirective } from '@syncfusion/ej2-vue-gantt';
//Component registration
export default {
  name: "App",
  components: {
    'ejs-gantt': GanttComponent,
    'e-columns': ColumnsDirective,
    'e-column': ColumnDirective
  }
}
</script>

The Gantt Chart and column directives are now registered and ready to use in this application.

Binding Gantt with data

Data for the Gantt Chart component is bound using the dataSource property. The value is defined in the Vue component and accepts either an array of JavaScript objects or a DataManager instance.

<template>
    <div>
       <ejs-gantt ref='gantt' :dataSource="data"></ejs-gantt>
   </div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
    {
        TaskID: 1,
        TaskName: 'Project Initiation',
        StartDate: new Date('04/02/2019'),
        EndDate: new Date('04/21/2019'),
        subtasks: [
            {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
            { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50  },
            { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
        ]
    },
    {
        TaskID: 5,
        TaskName: 'Project Estimation',
        StartDate: new Date('04/02/2019'),
        EndDate: new Date('04/21/2019'),
        subtasks: [
            { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
            { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
            { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
        ]
    },
];
</script>
<template>
     <div>
        <ejs-gantt ref='gantt' :dataSource="data"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";
export default {
name: "App",
  components: {
    'ejs-gantt': GanttComponent
  },
  data: function() {
      return{
            data: [
            {
                TaskID: 1,
                TaskName: 'Project Initiation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50  },
                    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                ]
            },
            {
                TaskID: 5,
                TaskName: 'Project Estimation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
                ]
            },
        ],
        };
  },
};
</script>

Mapping task fields

The data source fields that are required to render the tasks are mapped to the Gantt control using the taskFields property.

<template>
    <div>
        <ejs-gantt ref='gantt' :dataSource="data" id="GanttContainer" :taskFields="taskFields"
            :height="height"></ejs-gantt>
    </div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' :dataSource="data" id="GanttContainer" :taskFields="taskFields"
            :height="height"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
        };
    },
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Note : While creating a Syncfusion® Vue components using Direct Scripts, camelCased property (dataSource) names need to specify in the kebab-cased (data-source) equivalents.

Module injection

To create Vue Gantt Chart with additional features, inject the required modules. The following modules are used to extend Gantt Chart’s basic functionality.

  • Edit : Inject this module to use the editing feature.
  • Filter : Inject this module to use the filtering feature.
  • Sort : Inject this module to use the sorting feature.
  • Selection : Inject this module to use the selection feature.
  • Toolbar : Inject this module to use the toolbar items.
  • DayMarkers : Inject this module to highlight the days.

Additional feature modules are available here

Register required modules using the provide function in the <script> section and pass them as an array under the key ‘gantt’:

<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt , Edit, Filter, Sort } from "@syncfusion/ej2-vue-gantt";
export default {
  provide('gantt',  [ Edit, Filter, Sort ]);
};
</script>
<script>
import { GanttComponent , Edit, Filter, Sort } from "@syncfusion/ej2-vue-gantt";
export default {
  provide: {
    gantt: [ Edit, Filter, Sort ]
  }
};
</script>

Defining timeline

The Gantt chart provides an option to define the timeline using the timelineSettings property with various configuration options. This property allows customization of the Gantt timeline.

<template>
    <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
const timelineSettings = {
    topTier: {
        format: 'MMM dd, yyyy',
        unit: 'Week',
    },
    bottomTier: {
        unit: 'Day',
    },
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
            timelineSettings: {
                topTier: {
                    format: 'MMM dd, yyyy',
                    unit: 'Week',
                },
                bottomTier: {
                    unit: 'Day',
                },
            },
        };
    },
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Enabling toolbar

The toolbar property is used to add the toolbar items like Add, Remove, Edit, Update, Delete, Expand All,Collapse All in Gantt.

To use toolbar, inject the Toolbar module in the provide section.

<template>
     <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :toolbar="toolbar" :editSettings= "editSettings"></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt, Edit, Selection, Toolbar, DayMarkers  } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
const toolbar = ['Add', 'Edit', 'Update', 'Delete', 'Cancel', 'ExpandAll', 'CollapseAll'];
const editSettings = {
    allowAdding: true,
    allowEditing: true,
    allowDeleting: true,
    allowTaskbarEditing: true,
    showDeleteConfirmDialog: true
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :toolbar="toolbar" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent, Edit, Selection, Toolbar, DayMarkers } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
            toolbar: ['Add', 'Edit', 'Update', 'Delete', 'Cancel', 'ExpandAll', 'CollapseAll'],
            editSettings: {
                allowAdding: true,
                allowEditing: true,
                allowDeleting: true,
                allowTaskbarEditing: true,
                showDeleteConfirmDialog: true
            },
        };
    },
    provide: {
        gantt: [Edit, Selection, Toolbar, DayMarkers]
    }
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Enabling editing

The editing feature enables task modifications in the Gantt Chart component. It can be enabled by using the editSettings.allowEditing and editSettings.allowTaskbarEditing properties.

To use editing, inject the Edit module in the provide section.

The following editing options are available to update tasks in the Gantt:

  • Cell
  • Dialog
  • Taskbar
  • Connector line

Cell editing

Modify task details through cell editing by setting the edit mode property to Auto. To enable edit support, the Edit module must be injected into the Gantt. If the Edit module is not injected, no editing actions can be performed in the Gantt.

<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :toolbar="toolbar" :columns="columns" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt, Edit } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
const columns = [
    { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
    { field: 'TaskName', headerText: 'Task Name', width: '250' },
    { field: 'StartDate', headerText: 'Start Date', width: '150' },
    { field: 'Duration', headerText: 'Duration', width: '150' },
    { field: 'Progress', headerText: 'Progress', width: '150' },
];
const toolbar = ['Edit'];
const editSettings = {
    allowEditing: true,
    mode: "Auto"
};
provide('gantt', [Edit]);
</script>

<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height" :toolbar="toolbar" :columns="columns" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent, Edit } from "@syncfusion/ej2-vue-gantt";
export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
            columns: [
                { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
                { field: 'TaskName', headerText: 'Task Name', width: '250' },
                { field: 'StartDate', headerText: 'Start Date', width: '150' },
                { field: 'Duration', headerText: 'Duration', width: '150' },
                { field: 'Progress', headerText: 'Progress', width: '150' },
            ],
            toolbar: ['Edit'],
            editSettings: {
                allowEditing: true,
                mode: "Auto"
            },
        };
    },
    provide: {
        gantt: [Edit]
    }
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

When the edit mode is set to Auto, cells can be switched to editable mode by double‑clicking anywhere in the TreeGrid, and task details can be edited in the edit dialog by double‑clicking anywhere in the chart.

Dialog editing

Modify task details through a dialog by setting the edit mode property as Dialog.

<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :toolbar="toolbar" :columns="columns" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt, Edit } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
const columns = [
    { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
    { field: 'TaskName', headerText: 'Task Name', width: '250' },
    { field: 'StartDate', headerText: 'Start Date', width: '150' },
    { field: 'Duration', headerText: 'Duration', width: '150' },
    { field: 'Progress', headerText: 'Progress', width: '150' },
];
const toolbar = ['Edit'];
const editSettings = {
    allowEditing: true,
    mode: "Auto"
};
provide('gantt', [Edit]);
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :toolbar="toolbar" :columns="columns" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent, Edit } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
            columns: [
                { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
                { field: 'TaskName', headerText: 'Task Name', width: '250' },
                { field: 'StartDate', headerText: 'Start Date', width: '150' },
                { field: 'Duration', headerText: 'Duration', width: '150' },
                { field: 'Progress', headerText: 'Progress', width: '150' },
            ],
            toolbar: ['Edit'],
            editSettings: {
                allowEditing: true,
                mode: "Dialog"
            },
        };
    },
    provide: {
        gantt: [Edit]
    }
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

In dialog editing mode, the edit dialog appears when performing a double‑click action on both the TreeGrid and chart sides.

Taskbar editing

Modify task details through user interactions such as resizing and dragging the taskbar by enabling the allowTaskbarEditing property.

<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :toolbar="toolbar" :columns="columns" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt, Edit } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
const columns = [
    { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
    { field: 'TaskName', headerText: 'Task Name', width: '250' },
    { field: 'StartDate', headerText: 'Start Date', width: '150' },
    { field: 'Duration', headerText: 'Duration', width: '150' },
    { field: 'Progress', headerText: 'Progress', width: '150' },
];
const toolbar = ['Edit'];
const editSettings = {
    allowEditing: true,
    mode: "Auto"
};
provide('gantt', [Edit]);
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :toolbar="toolbar" :columns="columns" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent, Edit } from "@syncfusion/ej2-vue-gantt";
export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
            columns: [
                { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
                { field: 'TaskName', headerText: 'Task Name', width: '250' },
                { field: 'StartDate', headerText: 'Start Date', width: '150' },
                { field: 'Duration', headerText: 'Duration', width: '150' },
                { field: 'Progress', headerText: 'Progress', width: '150' },
            ],
            toolbar: ['Edit'],
            editSettings: {
                allowTaskbarEditing: true
            },
        };
    },
    provide: {
        gantt: [Edit]
    }
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Dependency editing

Modify task dependencies using mouse interactions by enabling the allowTaskbarEditing property along with mapping the task dependency data source field to the dependency property.

<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :toolbar="toolbar" :columns="columns" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt, Edit } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
const columns = [
    { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
    { field: 'TaskName', headerText: 'Task Name', width: '250' },
    { field: 'StartDate', headerText: 'Start Date', width: '150' },
    { field: 'Duration', headerText: 'Duration', width: '150' },
    { field: 'Progress', headerText: 'Progress', width: '150' },
];
const toolbar = ['Edit'];
const editSettings = {
    allowTaskbarEditing: true
};
provide('gantt', [Edit]);
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :toolbar="toolbar" :columns="columns" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent, Edit } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                parentID: 'ParentID'
            },
            columns: [
                { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
                { field: 'TaskName', headerText: 'Task Name', width: '250' },
                { field: 'StartDate', headerText: 'Start Date', width: '150' },
                { field: 'Duration', headerText: 'Duration', width: '150' },
                { field: 'Progress', headerText: 'Progress', width: '150' },
            ],
            toolbar: ['Edit'],
            editSettings: {
                allowTaskbarEditing: true
            },
        };
    },
    provide: {
        gantt: [Edit]
    }
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Enabling predecessors or task relationships

Predecessors or task dependencies in the Gantt Chart component are used to depict relationships between tasks.

  • Start to Start (SS): A task cannot start until its dependent task starts.
  • Start to Finish (SF): A task cannot finish until its dependent task starts.
  • Finish to Start (FS): A task cannot start until its dependent task completes.
  • Finish to Finish (FF): A task cannot finish until its dependent task completes.

Task relationships can be shown by using thedependency property, as demonstrated in the following code example:

<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            highlightWeekends='true'></ejs-gantt>
    </div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            highlightWeekends='true'></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
        };
    },
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Assigning resources

Resources can be displayed and assigned to each task in the Gantt Chart component. Create a collection of JSON objects that contain the id, name, unit, and group of the resources, and assign it to the resources property.

Map these fields to the Gantt control using the resourceFields property.

<template>
     <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields= "taskFields" :height= "height" :treeColumnIndex= "1" :resourceFields= "resourceFields" :resources= "resources" :highlightWeekends= "true" :labelSettings= "labelSettings"></ejs-gantt>
    </div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },

    { TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('04/02/2019'), Duration: 0, Progress: 50, resources: [1], ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform soil test', StartDate: new Date('04/02/2019'), Duration: 4, Predecessor: '2', Progress: 50, resources: [2, 3, 5], ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 0, Predecessor: '3', Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },

    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Predecessor: '4', Progress: 50, resources: [4], ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Predecessor: '6', Progress: 50, resources: [4, 8], ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 0, Predecessor: '7', resources: [12, 5], ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    dependency: 'Predecessor',
    child: 'subtasks',
    resourceInfo: 'resources'
};
const resourceFields = {
    id: 'resourceId',
    name: 'resourceName',
};
const resources = [
    { resourceId: 1, resourceName: 'Martin Tamer' },
    { resourceId: 2, resourceName: 'Rose Fuller' },
    { resourceId: 3, resourceName: 'Margaret Buchanan' },
    { resourceId: 4, resourceName: 'Fuller King' },
    { resourceId: 5, resourceName: 'Davolio Fuller' },
    { resourceId: 6, resourceName: 'Van Jack' },
    { resourceId: 7, resourceName: 'Fuller Buchanan' },
    { resourceId: 8, resourceName: 'Jack Davolio' },
    { resourceId: 9, resourceName: 'Tamer Vinet' },
    { resourceId: 10, resourceName: 'Vinet Fuller' },
    { resourceId: 11, resourceName: 'Bergs Anton' },
    { resourceId: 12, resourceName: 'Construction Supervisor' }
];
const labelSettings = {
    leftLabel: 'TaskName',
    rightLabel: 'resources'
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :treeColumnIndex="1" :resourceFields="resourceFields" :resources="resources" :highlightWeekends="true"
            :labelSettings="labelSettings"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },

                { TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('04/02/2019'), Duration: 0, Progress: 50, resources: [1], ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform soil test', StartDate: new Date('04/02/2019'), Duration: 4, Predecessor: '2', Progress: 50, resources: [2, 3, 5], ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 0, Predecessor: '3', Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },

                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Predecessor: '4', Progress: 50, resources: [4], ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Predecessor: '6', Progress: 50, resources: [4, 8], ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 0, Predecessor: '7', resources: [12, 5], ParentID: 5 }
            ],
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID',
                resourceInfo: 'resources'
            },
            height: '450px',

            resourceFields: {
                id: 'resourceId',
                name: 'resourceName',
            },

            resources: [
                { resourceId: 1, resourceName: 'Martin Tamer' },
                { resourceId: 2, resourceName: 'Rose Fuller' },
                { resourceId: 3, resourceName: 'Margaret Buchanan' },
                { resourceId: 4, resourceName: 'Fuller King' },
                { resourceId: 5, resourceName: 'Davolio Fuller' },
                { resourceId: 6, resourceName: 'Van Jack' },
                { resourceId: 7, resourceName: 'Fuller Buchanan' },
                { resourceId: 8, resourceName: 'Jack Davolio' },
                { resourceId: 9, resourceName: 'Tamer Vinet' },
                { resourceId: 10, resourceName: 'Vinet Fuller' },
                { resourceId: 11, resourceName: 'Bergs Anton' },
                { resourceId: 12, resourceName: 'Construction Supervisor' }
            ],
            labelSettings: {
                leftLabel: 'TaskName',
                rightLabel: 'resources'
            },
        };
    }
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Enable filtering

The filtering feature enables viewing a reduced set of records based on filter criteria. The Gantt component provides menu filtering support for each column. It can be enabled by setting the allowFiltering property to true along with injecting the Filter module, as shown in the following code example. The filtering feature can also be customized using the filterSettings property.

To use filtering, inject the Filter module in the provide section.

<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :columns="columns" :toolbar="toolbar" :allowFiltering="true" :timelineSettings="timelineSettings"
            :splitterSettings="splitterSettings" :labelSettings="labelSettings" :projectStartDate="projectStartDate"
            :projectEndDate="projectEndDate"></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt, Filter, Toolbar } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },

    { TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('04/02/2019'), Duration: 0, Progress: 50, resources: [1], ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform soil test', StartDate: new Date('04/02/2019'), Duration: 4, Predecessor: '2', Progress: 50, resources: [2, 3, 5], ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 0, Predecessor: '3', Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },

    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Predecessor: '4', Progress: 50, resources: [4], ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Predecessor: '6', Progress: 50, resources: [4, 8], ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 0, Predecessor: '7', resources: [12, 5], ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    dependency: 'Predecessor',
    parentID: 'ParentID'
};
const columns = [
    { field: 'TaskName', headerText: 'Task Name', width: '250', clipMode: 'EllipsisWithTooltip' },
    { field: 'StartDate', headerText: 'Start Date' },
    { field: 'Duration', headerText: 'Duration' },
    { field: 'EndDate', headerText: 'End Date' },
    { field: 'Predecessor', headerText: 'Predecessor' }
];
const toolbar = ['Search'];
const timelineSettings = {
    timelineUnitSize: 60,
    topTier: {
        format: 'MMM dd, yyyy',
        unit: 'Day',
    },
    bottomTier: {
        unit: 'Hour',
        format: 'h.mm a'
    },
};
const splitterSettings = {
    columnIndex: 3
};
const labelSettings = {
    rightLabel: 'TaskName',
};
const projectStartDate = new Date('04/02/2019');
const projectEndDate = new Date('04/21/2019');

provide('gantt', [Filter, Toolbar]);
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :columns="columns" :toolbar="toolbar" :allowFiltering="true" :timelineSettings="timelineSettings"
            :splitterSettings="splitterSettings" :labelSettings="labelSettings" :projectStartDate="projectStartDate"
            :projectEndDate="projectEndDate"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent, Filter, Toolbar } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },

                { TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('04/02/2019'), Duration: 0, Progress: 50, resources: [1], ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform soil test', StartDate: new Date('04/02/2019'), Duration: 4, Predecessor: '2', Progress: 50, resources: [2, 3, 5], ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 0, Predecessor: '3', Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },

                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Predecessor: '4', Progress: 50, resources: [4], ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Predecessor: '6', Progress: 50, resources: [4, 8], ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 0, Predecessor: '7', resources: [12, 5], ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                dependency: 'Predecessor',
                parentID: 'ParentID'
            },
            columns: [
                { field: 'TaskName', headerText: 'Task Name', width: '250', clipMode: 'EllipsisWithTooltip' },
                { field: 'StartDate', headerText: 'Start Date' },
                { field: 'Duration', headerText: 'Duration' },
                { field: 'EndDate', headerText: 'End Date' },
                { field: 'Predecessor', headerText: 'Predecessor' }
            ],
            toolbar: ['Search'],
            timelineSettings: {
                timelineUnitSize: 60,
                topTier: {
                    format: 'MMM dd, yyyy',
                    unit: 'Day',
                },
                bottomTier: {
                    unit: 'Hour',
                    format: 'h.mm a'
                },
            },
            splitterSettings: {
                columnIndex: 3
            },
            labelSettings: {
                rightLabel: 'TaskName',
            },
            projectStartDate: new Date('04/02/2019'),
            projectEndDate: new Date('04/21/2019')

        };
    },
    provide: {
        gantt: [Filter, Toolbar]
    }
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Enable sorting

The sorting feature enables ordering of records. It can be enabled by setting the allowSorting property to true. The Sort module must also be injected in the provide section. If the Sort module is not injected, sorting will not work when clicking the column headers. The sorting feature can be customized using the sortSettings property.

<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :columns="columns" :splitterSettings="splitterSettings" :allowSorting='true'></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt, Sort } from "@syncfusion/ej2-vue-gantt";
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
const splitterSettings = {
    columnIndex: 3
};
const columns = [
    { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
    { field: 'TaskName', headerText: 'Task Name', width: '250' },
    { field: 'StartDate', headerText: 'Start Date', width: '150' },
    { field: 'Duration', headerText: 'Duration', width: '150' },
    { field: 'Progress', headerText: 'Progress', width: '150' },
];
provide('gantt', [Sort]);
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :columns="columns" :splitterSettings="splitterSettings" :allowSorting='true'></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent, Sort } from "@syncfusion/ej2-vue-gantt";

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
            splitterSettings: {
                columnIndex: 3
            },
            columns: [
                { field: 'TaskID', headerText: 'Task ID', textAlign: 'Left', width: '100' },
                { field: 'TaskName', headerText: 'Task Name', width: '250' },
                { field: 'StartDate', headerText: 'Start Date', width: '150' },
                { field: 'Duration', headerText: 'Duration', width: '150' },
                { field: 'Progress', headerText: 'Progress', width: '150' },
            ],
        };
    },
    provide: {
        gantt: [Sort]
    }
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Defining event markers

The eventMarkers property in the Gantt Chart component is used to highlight important events in the chart area. This feature allows adding lines and labels to emphasize significant days in a project.

To highlight these days, inject the DayMarkers module in the provide section.

<template>
     <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :eventMarkers="eventMarkers"></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt, DayMarkers} from "@syncfusion/ej2-vue-gantt";
import { projectNewData } from './data-source.js';
const data = projectNewData;
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    dependency: 'Predecessor',
    child: 'subtasks'
};
const eventMarkers = [
    {
        day: new Date('04/09/2019'),
        label: 'Research phase'
    }, {
        day: new Date('04/30/2019'),
        label: 'Design phase'
    }, {
        day: new Date('05/23/2019'),
        label: 'Production phase'
    }, {
        day: new Date('06/20/2019'),
        label: 'Sales and marketing phase'
    }
];
provide('gantt',  [DayMarkers]);
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
     <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :eventMarkers="eventMarkers"></ejs-gantt>
    </div>
</template>
<script>
import { GanttComponent, DayMarkers} from "@syncfusion/ej2-vue-gantt";
import { projectNewData } from './data-source.js';

export default {
name: "App",
  components: {
    'ejs-gantt': GanttComponent
  },
  data: function() {
      return{
            data: projectNewData,
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             eventMarkers: [
                {
                    day: new Date('04/09/2019'),
                    label: 'Research phase'
                }, {
                    day: new Date('04/30/2019'),
                    label: 'Design phase'
                }, {
                    day: new Date('05/23/2019'),
                    label: 'Production phase'
                }, {
                    day: new Date('06/20/2019'),
                    label: 'Sales and marketing phase'
                }
            ]
      };
  },
  provide: {
      gantt: [DayMarkers]
  }
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';  
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Run the application

Now run the npm run serve command in the console, it will build your application and open in the web browser.

The following example shows a basic Gantt Chart:

<template>
    <div>
        <ejs-gantt id="gantt" :dataSource="data" :taskFields="taskFields" :height="height"></ejs-gantt>
    </div>
</template>

<script setup>
import { GanttComponent as EjsGantt } from '@syncfusion/ej2-vue-gantt';
const data = [
    { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

    { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
];
const height = '450px';
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    endDate: 'EndDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>
<template>
    <div>
        <ejs-gantt id="gantt" :dataSource="data" :taskFields="taskFields" :height="height"></ejs-gantt>
    </div>
</template>

<script>
import { GanttComponent } from '@syncfusion/ej2-vue-gantt';

export default {
    name: "App",
    components: {
        'ejs-gantt': GanttComponent
    },
    data: function () {
        return {
            data: [
                { TaskID: 1, TaskName: 'Project Initiation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50, ParentID: 1 },

                { TaskID: 5, TaskName: 'Project Estimation', StartDate: new Date('04/02/2019'), EndDate: new Date('04/21/2019'), ParentID: null },
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, ParentID: 5 }
            ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
        };
    },
};
</script>
<style>
@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-lists/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-splitbuttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import "../node_modules/@syncfusion/ej2-vue-gantt/styles/tailwind3.css";
</style>

Error handling

Error handling is used to identify errors, display them and develop recovery strategies to handle errors from gantt. In Gantt, error handling is done by using the actionFailure event. Some of the scenarios that this event handles are:

  • Invalid duration : The duration field accepts only numerical values with an optional decimal point. Entering non-numerical values triggers the actionFailure event and displays issue information in the event argument.
  • Invalid dependency: The dependency field accepts only a number followed by a predecessor type (FS, FF, SS, SF). Entering invalid values, such as special characters or incorrect predecessor types, triggers the actionFailure event and displays issue information in the event argument.
  • Invalid offset : The offset accepts only numerical values or their word equivalents followed by a unit. Entering invalid values, such as special characters triggers actionFailure event and displays issue information in the event argument.
  • Failure to map task fields : The data source fields necessary for rendering tasks should be mapped to the Gantt control using the taskFields property. Failure to map taskFields in the sample triggers actionFailure event and displays issue information in the event argument.
  • Failure to map resource fields : To assign resources to a task, resource fields should be mapped to the Gantt control using the resourceFields. Failure to map resourceFields in the sample triggers actionFailure event and displays issue information in the event argument.
  • Failure to map isPrimaryKey : isPrimaryKey field is crucial for CRUD operations. Failure to map id column in gantt column collection or isPrimaryKey field in one of the columns will trigger actionFailure event and display issue information in the event argument.
  • Invalid date format : format property under topTier and bottomTier determines how the timelines are displayed in the top tier and bottom tier of the Gantt chart timeline. If the format does not contain a valid standard date format, it triggers the actionFailure event, displaying issue information in the event argument.
  • Failure to map hasChildMapping : hasChildMapping property should configured for load-on-demand. Ensure it properly configured in the taskFields. Failure to map hasChildMapping in the load-on-demand sample triggers actionFailure event and displays issue information in the event argument.
  • Invalid day in event markers : day should configured in eventMarkers to render striplines in a particular day. Failure to configure the day in eventMarkers triggers actionFailure event and displays issue information in the event argument.

Additionally, TreeGrid side error handling information is also displayed from the Gantt actionFailure event. For more details on TreeGrid side error handling, refer here.

The following code example shows how to use the actionFailure event in the Gantt control to display an exception when isPrimaryKey is not configured properly in the Gantt Chart column.

<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :columns="columns" :splitterSettings="splitterSettings" :actionFailure='actionFailure'></ejs-gantt>
    </div>
</template>
<script setup>
import { provide } from "vue";
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
import { editingData } from './data-source.js';
const data = editingData;
const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
};
const height = '450px';
const splitterSettings = {
    columnIndex: 3
};
const columns = [
    { field: 'TaskName', headerText: 'Task Name', width: '150' },
    { field: 'StartDate', headerText: 'Start Date', width: '150' },
    { field: 'Duration', headerText: 'Duration', width: '150' },
    { field: 'Progress', headerText: 'Progress', width: '150' },
];
const actionFailure = function (args) {
    let span = document.createElement('span');
    let gantt = document.getElementsByClassName("e-gantt")[0].ej2_instances[0];
    gantt.element.parentNode.insertBefore(span, gantt.element);
    span.style.color = '#FF0000';
    span.innerHTML = args.error[0];
};
</script>
<template>
    <div>
        <ejs-gantt ref='gantt' id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
            :columns="columns" :splitterSettings="splitterSettings" :actionFailure='actionFailure'></ejs-gantt>
    </div>
</template>
<script>

import { GanttComponent } from "@syncfusion/ej2-vue-gantt";
import { editingData } from './data-source.js';

export default {
    name: "App",
    components: {
        "ejs-gantt": GanttComponent
    },
    data: function () {
        return {
            data: editingData,
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                duration: 'Duration',
                progress: 'Progress',
                parentID: 'ParentID'
            },
            height: '450px',
            splitterSettings: {
                columnIndex: 3
            },
            columns: [
                { field: 'TaskName', headerText: 'Task Name', width: '150' },
                { field: 'StartDate', headerText: 'Start Date', width: '150' },
                { field: 'Duration', headerText: 'Duration', width: '150' },
                { field: 'Progress', headerText: 'Progress', width: '150' },
            ]
        };
    },
    methods: {
        actionFailure: function (args) {
            let span = document.createElement('span');
            let gantt = document.getElementsByClassName("e-gantt")[0].ej2_instances[0];
            gantt.element.parentNode.insertBefore(span, gantt.element);
            span.style.color = '#FF0000';
            span.innerHTML = args.error[0];
        }
    }
};
</script>

The following screenshot represents the Gantt Exception handling in actionFailure event.

Error Handling