Getting Started with Next.js

22 May 20267 minutes to read

This guide shows how to integrate the React Gantt Chart component into a Next.js application using the App Router. For detailed component concepts and features, see the main Getting Started guide.

Prerequisites

Before you begin, ensure you have:

  • Node.js 18.17.0 or later
  • npm or yarn package manager
  • Basic knowledge of Next.js and React

Create a Next.js application

Create a new Next.js application with the recommended defaults (TypeScript, ESLint, Tailwind CSS, App Router):

npx create-next-app@latest my-gantt-app
cd my-gantt-app
yarn create next-app my-gantt-app
cd my-gantt-app

When prompted, select Yes to use the recommended Next.js defaults. This will set up your project with all necessary configurations.

Install the Gantt Chart package

Install the React Gantt Chart component:

npm install @syncfusion/ej2-react-gantt
yarn add @syncfusion/ej2-react-gantt

Add theme styles

Import the basic Gantt Chart styles in app/globals.css (replace the existing content):

@import '../node_modules/@syncfusion/ej2-base/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-gantt/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-grids/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-treegrid/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-layouts/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-popups/styles/tailwind3.css';

Note: When using features like editing, toolbar, filtering, or dialogs, you need to import additional component styles:

/* For editing, toolbar, and dialog features */
@import '../node_modules/@syncfusion/ej2-calendars/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-dropdowns/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-inputs/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-buttons/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-navigations/styles/tailwind3.css';
@import '../node_modules/@syncfusion/ej2-notifications/styles/tailwind3.css';

/* For rich text editor in dialog notes tab */
@import '../node_modules/@syncfusion/ej2-richtexteditor/styles/tailwind3.css';

Create sample data

Define a simple task list with hierarchical relationships. Each task must have a StartDate and either a Duration or EndDate to render properly.

const taskData = [
  {TaskID: 1, TaskName: 'Project initiation', StartDate: new Date('2024-04-01'), EndDate: new Date('2024-04-15')},
  {TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('2024-04-01'), Duration: 4, Progress: 70, ParentID: 1},
  {TaskID: 3, TaskName: 'Perform site survey', StartDate: new Date('2024-04-01'), Duration: 4, Progress: 50, ParentID: 1},
  {TaskID: 4, TaskName: 'Soil testing', StartDate: new Date('2024-04-01'), Duration: 3, Progress: 40, ParentID: 1},
  {TaskID: 5, TaskName: 'Project estimation', StartDate: new Date('2024-04-08'), EndDate: new Date('2024-04-18')},
  {TaskID: 6, TaskName: 'Develop floor plan', StartDate: new Date('2024-04-08'), Duration: 5, Progress: 30, ParentID: 5},
  {TaskID: 7, TaskName: 'Estimate project cost', StartDate: new Date('2024-04-08'), Duration: 5, Progress: 20, ParentID: 5}
];

Configure task fields

Map your data fields to Gantt Chart properties using taskFields:

const taskFields = {
  id: 'TaskID',
  name: 'TaskName',
  startDate: 'StartDate',
  duration: 'Duration',
  progress: 'Progress',
  parentID: 'ParentID'
};

Field mapping reference

Property Description Required
id Unique task identifier Yes
name Task display name Yes
startDate Task start date Yes
duration Task duration in days Yes*
progress Task completion percentage (0-100) No
parentID Parent task ID for hierarchy No

Render the Gantt component

Open app/page.tsx and replace its content:

'use client'
import { GanttComponent } from '@syncfusion/ej2-react-gantt';

export default function Home() {
  const taskData = [
    {TaskID: 1, TaskName: 'Project initiation', StartDate: new Date('2024-04-01'), EndDate: new Date('2024-04-15')},
    {TaskID: 2, TaskName: 'Identify site location', StartDate: new Date('2024-04-01'), Duration: 4, Progress: 70, ParentID: 1},
    {TaskID: 3, TaskName: 'Perform site survey', StartDate: new Date('2024-04-01'), Duration: 4, Progress: 50, ParentID: 1},
    {TaskID: 4, TaskName: 'Soil testing', StartDate: new Date('2024-04-01'), Duration: 3, Progress: 40, ParentID: 1},
    {TaskID: 5, TaskName: 'Project estimation', StartDate: new Date('2024-04-08'), EndDate: new Date('2024-04-18')},
    {TaskID: 6, TaskName: 'Develop floor plan', StartDate: new Date('2024-04-08'), Duration: 5, Progress: 30, ParentID: 5},
    {TaskID: 7, TaskName: 'Estimate project cost', StartDate: new Date('2024-04-08'), Duration: 5, Progress: 20, ParentID: 5}
  ];

  const taskFields = {
    id: 'TaskID',
    name: 'TaskName',
    startDate: 'StartDate',
    duration: 'Duration',
    progress: 'Progress',
    parentID: 'ParentID'
  };

  return (
    <GanttComponent dataSource={taskData} taskFields={taskFields} height='400px' />
  );
}

Note: The 'use client' directive is required for Next.js App Router to enable client-side interactivity.

Run the application

npm run dev
yarn run dev

Access the running application through your configured development URL.

Output

You will see a Gantt Chart with:

  • Task hierarchy with parent-child relationships
  • Timeline view showing task bars
  • Progress indicators on each task
  • Automatically calculated dates based on duration

The chart displays one parent task (“Project initiation”) with three subtasks shown in a tree structure. Task bars are rendered on the timeline, sized according to their duration and start dates.