Top tier and bottom tier in Vue Gantt component
11 Jun 202424 minutes to read
The Gantt component contains two tiers layout in timeline, you can customize the top tier and bottom tier using the topTier
and bottomTier
properties. Timeline tier’s unit can be defined by using the unit
property, and the format
property is used to define the date format of timeline cell. The count
property is used to define the number of units to be combined as a single cell and the formatter
property is used to define the custom method to format the date value of timeline cell.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields="taskFields" :height="height"
:timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
]
},
];
const height = '450px';
const taskFields = {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
};
const timelineSettings = {
topTier: {
format: 'MMM',
unit: 'Month'
},
bottomTier: {
unit: 'Day',
count: 2
}
};
</script>
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";
export default {
name: "App",
components: {
"ejs-gantt":GanttComponent
},
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
topTier: {
format: 'MMM',
unit: 'Month'
},
bottomTier: {
unit: 'Day',
count:2
}
},
};
},
};
</script>
Combining timeline cells
In the Gantt component, the timeline cells in top and bottom tiers can be combined with number of timeline units. This can be achieved by using the topTier.count
and bottomTier.count
properties. Refer to the following sample.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('09/16/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 120 , Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/04/2019'),
EndDate: new Date('09/18/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 }
]
},
];
const height = '450px';
const taskFields = {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
};
const timelineSettings = {
timelineUnitSize:100,
topTier: {
unit: 'Year'
},
bottomTier: {
unit: 'Month',
count:6
}
};
</script>
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";
export default {
name: "App",
components: {
"ejs-gantt":GanttComponent
},
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('09/16/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 120 , Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/04/2019'),
EndDate: new Date('09/18/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
timelineUnitSize:100,
topTier: {
unit: 'Year'
},
bottomTier: {
unit: 'Month',
count:6
}
},
};
},
};
</script>
Format value of timeline cell
In the Gantt component, you can format the value of top and bottom timeline cells using the standard date format string or the custom formatter method. This can be done using the topTier.format
, topTier.formatter
, bottomTier.format
and bottomTier.formatter
properties. The following example shows how to use the formatter method for timeline cells.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings" :projectStartDate="projectStartDate" :projectEndDate="projectEndDate"></ejs-gantt>
</div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('09/16/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 120 , Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/04/2019'),
EndDate: new Date('09/18/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 }
]
},
];
const height = '450px';
const taskFields = {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
};
const timelineSettings = {
topTier: {
unit: 'Month',
count: 3,
formatter: (date) => {
var month = date.getMonth();
if (month >= 0 && month <= 2) {
return 'Q1';
} else if (month >= 3 && month <= 5) {
return 'Q2';
} else if (month >= 6 && month <= 8) {
return 'Q3';
} else {
return 'Q4';
}
}
},
bottomTier: {
unit: 'Month',
format: 'MMM'
}
};
const projectStartDate = new Date('01/04/2019');
const projectEndDate = new Date('12/30/2019')
</script>
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings" :projectStartDate="projectStartDate" :projectEndDate="projectEndDate"></ejs-gantt>
</div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";
export default {
name: "App",
components: {
"ejs-gantt":GanttComponent
},
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('09/16/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 120 , Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/04/2019'),
EndDate: new Date('09/18/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
topTier: {
unit: 'Month',
count: 3,
formatter: (date) => {
var month = date.getMonth();
if (month >= 0 && month <= 2) {
return 'Q1';
} else if (month >= 3 && month <= 5) {
return 'Q2';
} else if (month >= 6 && month <= 8) {
return 'Q3';
} else {
return 'Q4';
}
}
},
bottomTier: {
unit: 'Month',
format: 'MMM'
}
},
projectStartDate: new Date('01/04/2019'),
projectEndDate: new Date('12/30/2019')
};
},
}
</script>
Timeline cell width
In the Gantt component, you can define the width value of timeline cell using the timelineSettings.timelineUnitSize
property. This value will be set to the bottom timeline cell, and the width value of top timeline cell will be calculated automatically based on bottom tier cell width using the topTier.unit
and timelineSettings.timelineUnitSize
properties. Refer to the following example.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script setup>
import { GanttComponent as EjsGantt } from "@syncfusion/ej2-vue-gantt";
const data = [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
]
},
];
const height = '450px';
const taskFields = {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
};
const timelineSettings = {
timelineUnitSize:200
};
</script>
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
</div>
</template>
<script>
import { GanttComponent } from "@syncfusion/ej2-vue-gantt";
export default {
name: "App",
components: {
"ejs-gantt":GanttComponent
},
data: function() {
return{
data: [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
]
},
],
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
endDate: 'EndDate',
duration: 'Duration',
progress: 'Progress',
dependency: 'Predecessor',
child: 'subtasks'
},
timelineSettings: {
timelineUnitSize:200
},
};
},
};
</script>