Non-working days/weekend are used to represent the non-productive days in a project. You can define the non-working days in a week using the workWeek
property in Gantt.
<template>
<div>
<ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :highlightWeekends='true' :workWeek="workWeek"></ejs-gantt>
</div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin, DayMarkers } from "@syncfusion/ej2-vue-gantt";
import { editingData } from './data-source.js';
Vue.use(GanttPlugin);
export default {
data: function() {
return{
data: editingData,
height: '450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
duration: 'Duration',
progress: 'Progress',
child: 'subtasks'
},
workWeek: ["Sunday","Monday","Tuesday","Wednesday","Thursday"],
};
},
provide: {
gantt: [ DayMarkers ]
}
};
</script>
By default, Saturdays and Sundays are considered as non-working days/weekend in a project.
In the Gantt component, you can make weekend as working day by setting theincludeWeekend
property to true.