ID | Job Name | Start Date | Duration | Progress | Dependency |
---|---|---|---|---|---|
1 | Product concept | 4/2/2024 | 5 days | 18 | |
2 | Defining the product and its usage | 4/2/2024 | 3 days | 30 | |
3 | Defining target audience | 4/2/2024 | 3 days | 0 | |
4 | Prepare product sketch and notes | 4/5/2024 | 2 days | 30 | 2FS |
5 | Concept approval | 4/8/2024 | 0 days | 0 | 3FS,4FS |
6 | Market research | 4/9/2024 | 8 days | 15 | |
7 | Demand analysis | 4/9/2024 | 4 days | 15 | |
8 | Customer strength | 4/9/2024 | 4 days | 30 | 5FS |
9 | Market opportunity analysis | 4/9/2024 | 4 days | 0 | 5FS |
10 | Competitor analysis | 4/15/2024 | 4 days | 30 | 7FS |
11 | Product strength analsysis | 4/15/2024 | 4 days | 0 | 9FS |
12 | Research complete | 4/18/2024 | 0 days | 0 | 10FS |
13 | Product design and development | 4/19/2024 | 20 days | 13 | |
14 | Functionality design | 4/19/2024 | 3 days | 30 | 12FS |
15 | Quality design | 4/19/2024 | 3 days | 0 | 12FS |
16 | Define reliability | 4/24/2024 | 2 days | 30 | 15FS |
17 | Identifying raw materials | 4/24/2024 | 2 days | 0 | 15FS |
18 | Define cost plan | 4/26/2024 | 2 days | 15 | |
19 | Manufacturing cost | 4/26/2024 | 2 days | 30 | 17FS |
20 | Selling cost | 4/26/2024 | 2 days | 0 | 17FS |
21 | Development of the final design | 4/30/2024 | 7 days | 8 | |
22 | Defining dimensions and package volume | 4/30/2024 | 2 days | 30 | 19FS,20FS |
23 | Develop design to meet industry standards | 5/2/2024 | 2 days | 0 | 22FS |
24 | Include all the details | 5/6/2024 | 3 days | 0 | 23FS |
25 | CAD computer-aided design | 5/9/2024 | 3 days | 30 | 24FS |
26 | CAM computer-aided manufacturing | 5/14/2024 | 3 days | 0 | 25FS |
27 | Design complete | 5/16/2024 | 0 days | 0 | 26FS |
28 | Prototype testing | 5/17/2024 | 4 days | 30 | 27FS |
29 | Include feedback | 5/17/2024 | 4 days | 0 | 28SS |
30 | Manufacturing | 5/23/2024 | 5 days | 30 | 28FS,29FS |
31 | Assembling materials to finsihed goods | 5/30/2024 | 5 days | 0 | 30FS |
32 | Feedback and testing | 6/6/2024 | 6 days | 47 | |
33 | Internal testing and feedback | 6/6/2024 | 3 days | 45 | 31FS |
34 | Customer testing and feedback | 6/11/2024 | 3 days | 50 | 33FS |
35 | Final product development | 6/14/2024 | 4 days | 30 | |
36 | Important improvements | 6/14/2024 | 4 days | 30 | 34FS |
37 | Address any unforeseen issues | 6/14/2024 | 4 days | 30 | 36SS |
38 | Final product | 6/20/2024 | 8 days | 15 | |
39 | Branding product | 6/20/2024 | 4 days | 0 | 37FS |
40 | Marketing and presales | 6/26/2024 | 4 days | 30 | 39FS |
Mar 24, 2024 | Mar 31, 2024 | Apr 07, 2024 | Apr 14, 2024 | Apr 21, 2024 | Apr 28, 2024 | May 05, 2024 | May 12, 2024 | May 19, 2024 | May 26, 2024 | Jun 02, 2024 | Jun 09, 2024 | Jun 16, 2024 | Jun 23, 2024 | Jun 30, 2024 |
---|
S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F |
---|
In this example, you can see how to render a Gantt chart with critical path. The default timeline view week-day mode is applied to Gantt chart. The dependency lines are enabled in this example to represent the execution order or the hierarchy between the phases.
The critical path is a series of tasks (or sometimes only a single task) that controls the calculated finish date of the project. If a task in a critical path is delayed, then the entire project will be delayed.
Gantt control features are segregated into individual feature-wise modules. To use a critical path, inject the
CriticalPath
module.
More information on the Critical Path feature can be found in this documentation section.