Timeline

In the Gantt component, timeline is used to represent the project duration as individual cells with defined unit and formats.

Timeline view modes

Gantt contains the following in-built timeline view modes:

  • Hour – Minute
  • Day – Hour
  • Week – Day
  • Month – Week
  • Year – Month

Timescale mode in the Gantt component can be defined using the timelineViewMode property, and you can define a timescale mode for the top tier and bottom tier using the topTier.unit and bottomTier.unit properties.

Week timeline mode

In the Week timeline mode, the upper part of the schedule header displays the weeks, whereas the bottom half of the header displays the days. Refer to the following code example.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
            {
                TaskID: 1,
                TaskName: 'Project Initiation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50  },
                    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                ]
            },
            {
                TaskID: 5,
                TaskName: 'Project Estimation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 4, Progress: 50 },
                    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 4, Progress: 50 },
                    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 4, Progress: 50 }
                ]
            },
        ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                timelineViewMode:'Week',
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Month timeline mode

In the Month timeline mode, the upper part of the schedule header displays the months, whereas the bottom header of the schedule displays its corresponding weeks. Refer to the following code example.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
            {
                TaskID: 1,
                TaskName: 'Project Initiation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 14, Progress: 50 },
                    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 14, Progress: 50  },
                    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 14, Progress: 50 },
                ]
            },
            {
                TaskID: 5,
                TaskName: 'Project Estimation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 14, Progress: 50 },
                    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 14, Progress: 50 },
                    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 14, Progress: 50 }
                ]
            },
        ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                timelineViewMode:'Month',
                timelineUnitSize:150,
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Year timeline mode

In the Year timeline mode, the upper schedule header displays the years whereas, the bottom header displays its corresponding months. Refer to the following code example.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
import { editingData  } from './data-source.js';
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
            {
                TaskID: 1,
                TaskName: 'Project Initiation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 54, Progress: 50 },
                    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 54, Progress: 50  },
                    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 54, Progress: 50 },
                ]
            },
            {
                TaskID: 5,
                TaskName: 'Project Estimation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 54, Progress: 50 },
                    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 54, Progress: 50 },
                    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 54, Progress: 50 }
                ]
            },
        ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                timelineViewMode:'Year',
                timelineUnitSize:70
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Day timeline mode

In the Day timeline mode, the upper part of the header displays the days whereas, the bottom schedule header displays its corresponding hours. Refer to the following code example.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
        {
            TaskID: 1,
            TaskName: 'Project Initiation',
            StartDate: new Date('04/02/2019'),
            EndDate: new Date('04/21/2019'),
            isParent:true,
            subtasks: [
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 2, Progress: 50,isParent:false },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 2, Progress: 50, resources: [2, 3, 5],isParent:false   },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 2,Predecessor:"2FS", Progress: 50,isParent:false  },
            ]
        },
    ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                timelineViewMode:'Day',
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Hour timeline mode

An Hour timeline mode tracks the tasks in minutes scale. In this mode, the upper schedule header displays hour scale and the lower schedule header displays its corresponding minutes.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
        {
            TaskID: 1,
            TaskName: 'Project Initiation',
            StartDate: new Date('04/02/2019'),
            EndDate: new Date('04/21/2019'),
            isParent:true,
            subtasks: [
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 2, Progress: 50,isParent:false },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 2, Progress: 50, resources: [2, 3, 5],isParent:false   },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 2,Predecessor:"2FS", Progress: 50,isParent:false  },
            ]
        },
    ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                timelineViewMode:'Hour',
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Top tier and bottom tier

The Gantt component contains two tiers layout in timeline, you can customize the top tier and bottom tier using the topTier and bottomTier properties. Timeline tier’s unit can be defined by using the unit property, and the format property is used to define the date format of timeline cell. The count property is used to define the number of units to be combined as a single cell and the formatter property is used to define the custom method to format the date value of timeline cell.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
            {
                TaskID: 1,
                TaskName: 'Project Initiation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50  },
                    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                ]
            },
            {
                TaskID: 5,
                TaskName: 'Project Estimation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
                ]
            },
        ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
            timelineSettings: {
                topTier: {
                    format: 'MMM',
                    unit: 'Month'
                },
                bottomTier: {
                    unit: 'Day',
                    count:2
                }
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Combining timeline cells

In the Gantt component, the timeline cells in top and bottom tiers can be combined with number of timeline units. This can be achieved by using the topTier.count and bottomTier.count properties. Refer to the following sample.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
        {
            TaskID: 1,
            TaskName: 'Project Initiation',
            StartDate: new Date('04/02/2019'),
            EndDate: new Date('09/16/2019'),
            subtasks: [
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50  },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 120 , Progress: 50 },
            ]
        },
        {
            TaskID: 5,
            TaskName: 'Project Estimation',
            StartDate: new Date('04/04/2019'),
            EndDate: new Date('09/18/2019'),
            subtasks: [
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 }
            ]
        },
    ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                timelineUnitSize:100,
                topTier: {
                   unit: 'Year'
                },
                    bottomTier: {
                    unit: 'Month',
                    count:6
                }
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Format value of timeline cell

In the Gantt component, you can format the value of top and bottom timeline cells using the standard date format string or the custom formatter method. This can be done using the topTier.format, topTier.formatter, bottomTier.format and bottomTier.formatter properties. The following example shows how to use the formatter method for timeline cells.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings" :projectStartDate="projectStartDate" :projectEndDate="projectEndDate"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
        {
            TaskID: 1,
            TaskName: 'Project Initiation',
            StartDate: new Date('04/02/2019'),
            EndDate: new Date('09/16/2019'),
            subtasks: [
                { TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50 },
                { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 120, Progress: 50  },
                { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 120 , Progress: 50 },
            ]
        },
        {
            TaskID: 5,
            TaskName: 'Project Estimation',
            StartDate: new Date('04/04/2019'),
            EndDate: new Date('09/18/2019'),
            subtasks: [
                { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
                { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 },
                { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 120, Progress: 50 }
            ]
        },
    ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                 topTier: {
            unit: 'Month',
            count: 3,
            formatter: (date) => {
                var month = date.getMonth();
                if (month >= 0 && month <= 2) {
                    return 'Q1';
                } else if (month >= 3 && month <= 5) {
                    return 'Q2';
                } else if (month >= 6 && month <= 8) {
                    return 'Q3';
                } else {
                    return 'Q4';
                }

            }
            },
            bottomTier: {
            unit: 'Month',
            format: 'MMM'
        }
      },
       projectStartDate: new Date('01/04/2019'),
       projectEndDate: new Date('12/30/2019')
  };
},
}
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Timeline cell width

In the Gantt component, you can define the width value of timeline cell using the timelineSettings.timelineUnitSize property. This value will be set to the bottom timeline cell, and the width value of top timeline cell will be calculated automatically based on bottom tier cell width using the topTier.unit and timelineSettings.timelineUnitSize properties. Refer to the following example.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
            {
                TaskID: 1,
                TaskName: 'Project Initiation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50  },
                    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                ]
            },
            {
                TaskID: 5,
                TaskName: 'Project Estimation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
                ]
            },
        ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                timelineUnitSize:200
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Week start day customization

In the Gantt component, you can customize the week start day using the weekStartDay property. By default, the weekStartDay is set to 0, which specifies the Sunday as a start day of the week. But, you can customize the week start day by using the following code example.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
            {
                TaskID: 1,
                TaskName: 'Project Initiation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50  },
                    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                ]
            },
            {
                TaskID: 5,
                TaskName: 'Project Estimation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
                ]
            },
        ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                timelineViewMode:'Week',
                weekStartDay:3
            },
      };
  },  
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>

Customize automatic timescale update action

In the Gantt component, the schedule timeline will be automatically updated when the tasks date values are updated beyond the project start date and end date ranges. This can be enabled or disabled using the updateTimescaleView property.

Source
Preview
app.vue
<template>
     <div>
        <ejs-gantt id="GanttContainer" :dataSource="data" :taskFields = "taskFields" :height = "height" :timelineSettings="timelineSettings" :editSettings="editSettings"></ejs-gantt>
    </div>
</template>
<script>
import Vue from "vue";
import { GanttPlugin,Edit } from "@syncfusion/ej2-vue-gantt";
Vue.use(GanttPlugin);
export default {
  data: function() {
      return{
            data: [
            {
                TaskID: 1,
                TaskName: 'Project Initiation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    {  TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                    { TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50  },
                    { TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 4, Progress: 50 },
                ]
            },
            {
                TaskID: 5,
                TaskName: 'Project Estimation',
                StartDate: new Date('04/02/2019'),
                EndDate: new Date('04/21/2019'),
                subtasks: [
                    { TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 },
                    { TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50 }
                ]
            },
        ],
            height: '450px',
            taskFields: {
                id: 'TaskID',
                name: 'TaskName',
                startDate: 'StartDate',
                endDate: 'EndDate',
                duration: 'Duration',
                progress: 'Progress',
                dependency: 'Predecessor',
                child: 'subtasks'
            },
             timelineSettings: {
                updateTimescaleView:false
            },
            editSettings:{
                allowEditing:true,
                allowTaskbarEditing:true
                }
      };
  },
  provide: {
      gantt: [ Edit ]
  },
};
</script>

<style>
@import '../node_modules/@syncfusion/ej2-vue-gantt/styles/material.css';
</style>