Duration unit in EJ2 JavaScript Gantt control
2 May 202311 minutes to read
Duration units
In Gantt, the task’s duration value can be measured by the following duration units,
- Day
- Hour
- Minute
In Gantt, we can define duration unit for whole project by using durationUnit
property, when we defines the value for this property, this unit will be applied for all task which don’t has duration unit value. And each task in the project can be defined with different duration units and the duration unit of a task can be defined by the following ways,
- Using
taskFields.durationUnit
property, to map the duration unit data source field. - Defining the duration unit value along with the duration field in the data source.
Mapping the duration unit field
The below code snippet explains the mapping of duration unit data source field to the Gantt control using the taskFields.durationUnit
property.
var ganttData = [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: 2, DurationUnit:'day', Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: 12,DurationUnit:'hour', Progress: 70 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: 240,DurationUnit:'minute', Progress: 80 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: 3, DurationUnit:'hour', Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: 3, Progress: 50, DurationUnit:'day' },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: 480, DurationUnit:'minute', Progress: 70 }
]
},
];
var ganttChart = new ej.gantt.Gantt({
dataSource: ganttData,
height:'450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
duration: 'Duration',
progress: 'Progress',
durationUnit:'DurationUnit',
child: 'subtasks'
},
splitterSettings:{
columnIndex:4
}
});
ganttChart.appendTo('#Gantt');
<!DOCTYPE html><html lang="en"><head>
<title>EJ2 Gantt</title>
<meta charset="utf-8">
<meta name="viewport" content="width=device-width, initial-scale=1.0">
<meta name="description" content="Typescript Gantt Controls">
<meta name="author" content="Syncfusion">
<link href="index.css" rel="stylesheet">
<link href="https://cdn.syncfusion.com/ej2/material.css" rel="stylesheet" type="text/css">
<script src="https://cdn.syncfusion.com/ej2/23.1.36/dist/ej2.min.js" type="text/javascript"></script>
<script src="https://cdn.syncfusion.com/ej2/syncfusion-helper.js" type ="text/javascript"></script>
</head>
<body>
<div id="container">
<div id="Gantt"></div>
</div>
<script>
var ele = document.getElementById('container');
if(ele) {
ele.style.visibility = "visible";
}
</script>
<script src="index.js" type="text/javascript"></script>
</body></html>
NOTE
The default value of thedurationUnit
property isday
.
Defining duration unit along with duration field
Duration units for the tasks can also be defined along with the duration values, the below code snippet explains the duration unit for a task along with duration value,
var ganttData = [
{
TaskID: 1,
TaskName: 'Project Initiation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
isParent:true,
subtasks: [
{ TaskID: 2, TaskName: 'Identify Site location', StartDate: new Date('04/02/2019'), Duration: '3days', Progress: 50 },
{ TaskID: 3, TaskName: 'Perform Soil test', StartDate: new Date('04/02/2019'), Duration: '12hours', Progress: 70 },
{ TaskID: 4, TaskName: 'Soil test approval', StartDate: new Date('04/02/2019'), Duration: '1800minutes', Progress: 80 },
]
},
{
TaskID: 5,
TaskName: 'Project Estimation',
StartDate: new Date('04/02/2019'),
EndDate: new Date('04/21/2019'),
isParent:true,
subtasks: [
{ TaskID: 6, TaskName: 'Develop floor plan for estimation', StartDate: new Date('04/04/2019'), Duration: '12hours',Progress: 50 },
{ TaskID: 7, TaskName: 'List materials', StartDate: new Date('04/04/2019'), Duration: '3days', Progress: 50 },
{ TaskID: 8, TaskName: 'Estimation approval', StartDate: new Date('04/04/2019'), Duration: '480minutes', Progress: 70 }
]
},
];
var ganttChart = new ej.gantt.Gantt({
dataSource: ganttData,
height:'450px',
taskFields: {
id: 'TaskID',
name: 'TaskName',
startDate: 'StartDate',
duration: 'Duration',
progress: 'Progress',
child: 'subtasks'
},
splitterSettings:{
columnIndex:4
}
});
ganttChart.appendTo('#Gantt');
<!DOCTYPE html><html lang="en"><head>
<title>EJ2 Gantt</title>
<meta charset="utf-8">
<meta name="viewport" content="width=device-width, initial-scale=1.0">
<meta name="description" content="Typescript Gantt Controls">
<meta name="author" content="Syncfusion">
<link href="index.css" rel="stylesheet">
<link href="https://cdn.syncfusion.com/ej2/material.css" rel="stylesheet" type="text/css">
<script src="https://cdn.syncfusion.com/ej2/23.1.36/dist/ej2.min.js" type="text/javascript"></script>
<script src="https://cdn.syncfusion.com/ej2/syncfusion-helper.js" type ="text/javascript"></script>
</head>
<body>
<div id="container">
<div id="Gantt"></div>
</div>
<script>
var ele = document.getElementById('container');
if(ele) {
ele.style.visibility = "visible";
}
</script>
<script src="index.js" type="text/javascript"></script>
</body></html>
NOTE:
The edit type of the duration column in Gantt is string, to support editing the duration field along with duration units.