Non-working days in a project can be displayed in the Gantt component using the Holidays property. Each holiday can be defined with the following properties:

  • From: Defines start date of the holiday(s).
  • To: Defines end date of the holiday(s).
  • Label: Defines the description or label for the holiday.
  • CssClass: Formats the holidays label in the Gantt chart.

The following code example shows how to display the non-working days in the Gantt component.

@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt DataSource="@TaskCollection" Height="450px" Width="900px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
             Duration="Duration" Progress="Progress" Child="SubTasks">
    </GanttTaskFields>
    <GanttHolidays>
        <GanttHoliday From="04/11/2019" To="04/12/2019" Label="Public holidays"
              CssClass="e-custom-holiday"></GanttHoliday>
        <GanttHoliday From="04/01/2019" To="04/01/2019" Label="Public holiday"
              CssClass="e-custom-holiday"></GanttHoliday>
    </GanttHolidays>
</EjsGantt>
@code{
    public List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30
                }
            })
        }
    };
    return Tasks;
}
}
<style>
    .e-gantt .e-gantt-chart .e-custom-holiday {
        background-color: #e82869;
    }
</style>

The following screenshot shows the output of Holidays in Gantt component.

Alt text