Search results

Appearance And Customization

Taskbar customization

Taskbar Height

Height of child taskbars and parent taskbars can be customized by using TaskbarHeight property. The following code example shows how to use the property.

@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt DataSource="@TaskCollection" Height="450px" Width="900px" RowHeight=60 TaskbarHeight=50>
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
           Duration="Duration" Progress="Progress" Child="SubTasks">
    </GanttTaskFields>
</EjsGantt>
@code{
    public List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30
                }
            })
        }
    };

    return Tasks;
}
}

Alt text

NOTE The TaskbarHeight property accepts only pixel value.

Conditional formatting

The default taskbar UI can be replaced with custom templates using the QueryTaskbarInfo event. The following code example shows customizing the taskbar UI based on task progress values in the Gantt component.

@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt DataSource="@TaskCollection" Height="450px" Width="900px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
           Duration="Duration" Progress="Progress" Child="SubTasks">
    </GanttTaskFields>
    <GanttEvents QueryTaskbarInfo="QueryTaskbarInfo" TValue="TaskData"></GanttEvents>
</EjsGantt>
@code{
    public void QueryTaskbarInfo(IQueryTaskbarInfoEventArgs<TaskData> args)
    {
        if (args.Data.TaskData.Progress == 30)
        {
            args.ProgressBarBgColor = "#FFC0CB";
        } else if (args.Data.TaskData.Progress == 40) {
            args.ProgressBarBgColor = "#FFFFE0";
        }
    }
    public List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30
                }
            })
        }
    };

    return Tasks;
}
}

Alt text

Taskbar template

You can design your own taskbars to view the tasks in Gantt by using TaskbarTemplate property. And it is possible to map the template script element’s ID value to this property. It is also possible to customize the parent taskbars and milestones with custom templates by using ParentTaskbarTemplate and MilestoneTemplate properties.

@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt ModelType="@TemplateModel" DataSource="@TaskCollection" ProjectStartDate="03/05/2018 06:00 PM" ProjectEndDate="03/05/2018 09:50 PM" DateFormat="hh:mm a" Height="450px" Width="700px" RowHeight="75" DurationUnit="DurationUnit.Minute">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" Dependency="Predecessor" Child="SubTasks"></GanttTaskFields>
    <GanttColumns>
        <GanttColumn Field="TaskId" HeaderText="Event Id"></GanttColumn>
        <GanttColumn Field="TaskName" HeaderText="Event Name"></GanttColumn>
        <GanttColumn Field="StartDate" HeaderText="Start Time"></GanttColumn>
        <GanttColumn Field="EndDate" HeaderText="End Time"></GanttColumn>
        <GanttColumn Field="Winner" HeaderText="Winner"></GanttColumn>
        <GanttColumn Field="Movie" HeaderText="Movie"></GanttColumn>
        <GanttColumn Field="Performance" HeaderText="Moments / Performance Details"></GanttColumn>
    </GanttColumns>
    <GanttTemplates>
        <TaskbarTemplate>
            @if ((context as GanttTaskTemplateModel).GanttProperties.TaskName == "Oscar moments")
            {
                <div class="e-gantt-child-taskbar e-custom-moments" style="height:68px;border-radius:5px;">
                    <span class="e-task-label" style="position:absolute;top:15px;font-size:12px;text-overflow:ellipsis;height:90%;overflow:hidden;">@((context as GanttTaskTemplateModel).Performance)</span>
                </div>
            }
            else
            {
                <div class="e-gantt-parent-taskbar e-custom-parent" style="height:68px;border-radius:5px;text-overflow:ellipsis;">
                    @if (!string.IsNullOrEmpty(((context as GanttTaskTemplateModel).Winner)) && !string.IsNullOrEmpty(((context as GanttTaskTemplateModel).Movie)))
                    {
                        <span class="e-task-label" style="position:absolute; top:13px;font-size:14px;">@((context as GanttTaskTemplateModel).Winner)</span>
                        <span class="e-task-label" style="position:absolute;top:33px;font-size:10px;text-overflow:ellipsis;">@((context as GanttTaskTemplateModel).Movie)</span>
                    }
                </div>
            }
        </TaskbarTemplate>
        <MilestoneTemplate>
            <div style="margin-top:-7px;">
                <div class="e-gantt-milestone" style="position:absolute;">
                    <div class="e-milestone-top" style="border-right-width:26px; margin-top: -24px;border-left-width:26px;border-bottom-width:26px;"></div>
                    <div class="e-milestone-bottom" style="top:26px;border-right-width:26px; border-left-width:26px; border-top-width:26px;"></div>
                </div>
            </div>
        </MilestoneTemplate>
    </GanttTemplates>
    <GanttTimelineSettings TimelineUnitSize="60">
        <GanttTopTierSettings Unit="TimelineViewMode.Hour" Format="MMM dd, yyyy"></GanttTopTierSettings>
        <GanttBottomTierSettings Unit="TimelineViewMode.Minutes" Count="2" Format="h:mm a"></GanttBottomTierSettings>
    </GanttTimelineSettings>
    <GanttDayWorkingTimeCollection>
        <GanttDayWorkingTime From="0" To="24"></GanttDayWorkingTime>
    </GanttDayWorkingTimeCollection>
</EjsGantt>
<style>
    .e-custom-parent {
        background-color: #6d619b;
        border: 1px solid #3f51b5;
    }
    .e-custom-moments {
        background-color: #7ab748;
        border: 1px solid #3f51b5;
    }
    .e-milestone-top {
        border-bottom-color: #7ab748 !important;
        border-bottom: 1px solid #3f51b5;
    }
    .e-milestone-bottom {
        border-top-color: #7ab748 !important;
        border-top: 1px solid #3f51b5;
    }
</style>

@code {
    public class GanttTaskTemplateModel {
        public string Performance { get; set; }
        public string Winner { get; set; }
        public string Movie { get; set; }
        public TaskProperties GanttProperties { get; set; }
    }
    public class TaskProperties {
        public string TaskName { get; set; }
        public double Duration { get; set; }
    }
    public GanttTaskTemplateModel TemplateModel = new GanttTaskTemplateModel();
    public List<TaskbarData> TaskCollection { get; set; }
    protected override void OnInitialized() {
        this.TaskCollection = GetTaskCollection();
    }
    public class TaskData {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public string Predecessor { get; set; }
    }
    public class TaskbarData : TaskData {
        public string Performance { get; set; }
        public string Winner { get; set; }
        public string Movie { get; set; }
    }
    public static List<TaskbarData> GetTaskCollection() {
        List<TaskbarData> Tasks = new List<TaskbarData>() {
            new TaskbarData() {
                TaskId = 1,
                TaskName = "Oscar moments",
                StartDate = new DateTime(2018, 03, 05, 18, 0, 0),
                EndDate = new DateTime(2018, 03, 05, 18, 15, 0),
                Winner = "",
                Performance = "90th Academy awards kicks-off and Jimmy kimmel hosts the show"
            },
            new TaskbarData() {
                TaskId = 2,
                TaskName = "Actor in a supporting role",
                StartDate = new DateTime(2018, 03, 05, 18, 16, 0),
                EndDate = new DateTime(2018, 03, 05, 18, 25, 0),
                Predecessor = "1",
                Winner = "Sam Rockwell",
                Movie = "Three Billboards Outside Ebbing, Missouri."
            },
            new TaskbarData() {
                TaskId = 3,
                TaskName = "Hair and makeup",
                StartDate = new DateTime(2018, 03, 05, 18, 26, 0),
                EndDate = new DateTime(2018, 03, 05, 18, 32, 0),
                Predecessor = "2",
                Movie = "Darkest Hour"
            },
            new TaskbarData() {
                TaskId = 4,
                TaskName = "Costume design",
                StartDate = new DateTime(2018, 03, 05, 18, 33, 0),
                EndDate = new DateTime(2018, 03, 05, 18, 40, 0),
                Predecessor = "3",
                Winner = "Mark Bridges",
                Movie = "Phantom Thread"
            },
            new TaskbarData() {
                TaskId = 5,
                TaskName = "Documentary feature",
                StartDate = new DateTime(2018, 03, 05, 18, 41, 0),
                EndDate = new DateTime(2018, 03, 05, 18, 58, 0),
                Predecessor = "4",
                Winner = "Bryan Fogel",
                Movie = "Icarus"
            },
            new TaskbarData() {
                TaskId = 6,
                TaskName = "Best sound editing and sound mixing",
                StartDate = new DateTime(2018, 03, 05, 18, 59, 0),
                EndDate = new DateTime(2018, 03, 05, 19, 10, 0),
                Predecessor = "5",
                Winner = "Richard King and Alex Gibson",
                Movie = "Dunkirk"
            },
            new TaskbarData() {
                TaskId = 7,
                TaskName = "Production design",
                StartDate = new DateTime(2018, 03, 05, 19, 11, 0),
                EndDate = new DateTime(2018, 03, 05, 19, 15, 0),
                Predecessor = "6",
                Movie = "The Shape of Water"
            },
            new TaskbarData() {
                TaskId = 8,
                TaskName = "Oscar performance",
                StartDate = new DateTime(2018, 03, 05, 19, 16, 0),
                EndDate = new DateTime(2018, 03, 05, 19, 23, 0),
                Predecessor = "7",
                Performance = "Second performance of the night is 'Remember Me' from Coco",
            },
            new TaskbarData() {
                TaskId = 9,
                TaskName = "90th Academy awards wind-up",
                StartDate = new DateTime(2018, 03, 05, 21, 30, 0),
                EndDate = new DateTime(2018, 03, 05, 21, 30, 0),
                Predecessor = "31",
                Duration = "0",
                Performance = "90th Academy awards wind-up"
            }
        };
    return Tasks;
    }
}

Alt text

Task labels

The Gantt component maps any data source fields to task labels using the LabelSettings.LeftLabel, LabelSettings.RightLabel, and LabelSettings.TaskLabel properties. You can customize the task labels with templates.

@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt ModelType="@TemplateCollections" DataSource="@TaskCollection" Height="450px" Width="900px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
                     Duration="Duration" Progress="Progress" Child="SubTasks">
    </GanttTaskFields>
    <GanttLabelSettings LeftLabel="TaskId">
        <RightLabelTemplate>
            <div class="e-right-label-inner-div" style="height:22px;margin-top:7px;">
                <span class="e-label">Task Name: @((context as GanttLabelTemplate).TaskName)</span>
            </div>
        </RightLabelTemplate>
        <TaskLabelTemplate>
            <div>@((context as GanttLabelTemplate).Progress)%</div>
        </TaskLabelTemplate>
    </GanttLabelSettings>
</EjsGantt>
@code{
    public List<TaskData> TaskCollection { get; set; }
    public GanttLabelTemplate TemplateCollections = new GanttLabelTemplate();
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class GanttLabelTemplate
    {
        public string TaskName { get; set; }
        public int Progress { get; set; }
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30
                }
            })
        }
    };

    return Tasks;
}
}
<style>
    .e-task-label {
        position: absolute;
    }
</style>

Alt text

Connector lines

The width and background color of connector lines in Gantt can be customized using the ConnectorLineWidth and ConnectorLineBackground properties. The following code example shows how to use these properties.

@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt DataSource="@TaskCollection" Height="450px" Width="800px" ConnectorLineWidth="3" ConnectorLineBackground="red">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" Child="SubTasks" Dependency="Predecessor">
    </GanttTaskFields>
</EjsGantt>

@code{
    public List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public string Predecessor { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                    Predecessor = "2"
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                    Predecessor = "3"
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                    Predecessor = "4"
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                    Predecessor = "6"
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30,
                    Predecessor = "7"
                },
            })
        }
    };

    return Tasks;
}
}

Alt text

Customize rows and cells

While rendering the TreeGrid part in Gantt, the RowDataBound and QueryCellInfo events trigger for every row and cell. Using these events, you can customize the rows and cells. The following code example shows how to customize the cell and row elements using these events.

@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt DataSource="@TaskCollection" Height="450px" Width="900px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate"
           Duration="Duration" Progress="Progress" Child="SubTasks">
    </GanttTaskFields>
    <GanttColumns>
        <GanttColumn Field="TaskId" Width="150"></GanttColumn>
        <GanttColumn Field="TaskName" HeaderText="Task Name" Width="250"></GanttColumn>
        <GanttColumn Field="Progress" Width="150"></GanttColumn>
        <GanttColumn Field="StartDate" HeaderText="Start Date" Width="150"></GanttColumn>
        <GanttColumn Field="Duration" HeaderText="Duration" Width="150"></GanttColumn>
    </GanttColumns>
    <GanttSplitterSettings ColumnIndex=3></GanttSplitterSettings>
    <GanttEvents QueryCellInfo="QueryCellInfo" RowDataBound="RowDataBound" TValue="TaskData"></GanttEvents>
</EjsGantt>
<style>
    .custom-row {
        background-color: #90EE90;
    }
    .yellow-cell {
        background-color: #FFFF00;
    }
    .red-cell {
        background-color: #20B2AA;
    }
</style>
@code{
    public void QueryCellInfo(QueryCellInfoEventArgs<TaskData> args)
    {
        if (args.Column.Field == "Progress")
        {
            if (args.Data.TaskData.Progress == 30)
            {
                args.Cell.AddClass(new string[] { "yellow-cell" });
            }
            else
            {
                args.Cell.AddClass(new string[] { "red-cell" });
            }
        }
    }
    public void RowDataBound(RowDataBoundEventArgs<TaskData> args)
    {
        if(args.Data.TaskData.TaskId == 4) {
            args.Row.AddClass(new string[] { "custom-row" });
        }
    }
    public List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30
                }
            })
        }
    };

    return Tasks;
}
}

Alt text

Grid lines

In the Gantt component, you can show or hide the grid lines in the TreeGrid side and chart side by using the GridLines property.

The following options are available in the Gantt component for rendering the grid lines:

  • Horizontal: The horizontal grid lines alone will be visible.
  • Vertical: The vertical grid lines alone will be visible.
  • Both: Both the horizontal and vertical grid lines will be visible on the TreeGrid and chart sides.
  • None: Gridlines will not be visible on TreeGrid and chart sides.

By default, the GridLines property is set to Horizontal type.

@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt DataSource="@TaskCollection" Height="450px" Width="800px" GridLines="GridLine.Both">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" Child="SubTasks">
    </GanttTaskFields>
</EjsGantt>

@code{
    public List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30,
                },
            })
        }
    };

    return Tasks;
}
}

Alt text

Splitter

In the Gantt component, the Splitter separates the TreeGrid section from the Chart section. You can change the position of the Splitter when loading the Gantt component using the SplitterSettings property. By splitting the TreeGrid from the chart, the width of the TreeGrid and chart sections will vary in the component. The SplitterSettings.Position property denotes the percentage of the TreeGrid section’s width to be rendered and this property supports both pixels and percentage values. You can define the splitter position as column index value using the SplitterSettings.ColumnIndex property. You can also define the splitter position with built-in splitter view modes by using the SplitterSettings.View property. The following list is the possible values for this property:

  • Default: Shows Grid side and Gantt side.
  • Grid: Shows Grid side alone in Gantt.
  • Chart: Shows chart side alone in Gantt.
@using Syncfusion.EJ2.Blazor.Gantt
<EjsGantt DataSource="@TaskCollection" Height="450px" Width="800px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" Child="SubTasks">
    </GanttTaskFields>
    <GanttSplitterSettings Position="80%"></GanttSplitterSettings>
</EjsGantt>

@code{
    public List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30,
                },
            })
        }
    };

    return Tasks;
}
}

Alt text

Change splitter position dynamically

In Gantt, we can change the splitter position dynamically by using SetSplitterPosition method. We can change the splitter position by passing value and type parameter to SetSplitterPosition method. Type parameter will accept one of the following values ‘position’, ‘columnIndex’, ‘viewType’. The following code example shows how to use this method.

@using Syncfusion.EJ2.Blazor.Gantt
@using Syncfusion.EJ2.Blazor.DropDowns
<button @onclick="UpdateSplitterByPosition">Update splitter by position</button>
<button @onclick="UpdateSplitterByIndex">Update splitter by index</button>
<EjsDropDownList TValue="@SplitterView" DataSource="@SplitterViews" Width="200">
    <DropDownListFieldSettings Value="ID" Text="Text"></DropDownListFieldSettings>
    <DropDownListEvents TValue="string" ValueChange="OnChange"></DropDownListEvents>
</EjsDropDownList>
<EjsGantt @ref="Gantt" @ref:suppressField DataSource="@TaskCollection" Height="450px" Width="800px">
    <GanttTaskFields Id="TaskId" Name="TaskName" StartDate="StartDate" EndDate="EndDate" Duration="Duration" Progress="Progress" Child="SubTasks">
    </GanttTaskFields>
</EjsGantt>

@code{
    public EjsGantt<TaskData> Gantt;
    public class SplitterView
    {
        public string ID { get; set; }
        public string Text { get; set; }
    }
    public List<SplitterView>SplitterViews = new List<SplitterView>
    {
        new SplitterView() { ID= "Default", Text= "Default" },
        new SplitterView() { ID= "Grid", Text= "Grid" },
        new SplitterView() { ID= "Chart", Text= "Chart" },
    };
    public void OnChange(ChangeEventArgs<string>args)
    {
        this.Gantt.SetSplitterPosition(args.Value, "view");
    }
    public void UpdateSplitterByPosition()
    {
    this.Gantt.SetSplitterPosition("50%", "position");
    }
    public void UpdateSplitterByIndex()
    {
    this.Gantt.SetSplitterPosition(0, "columnIndex");
    }
    public List<TaskData> TaskCollection { get; set; }
    protected override void OnInitialized()
    {
        this.TaskCollection = GetTaskCollection();
    }

    public class TaskData
    {
        public int TaskId { get; set; }
        public string TaskName { get; set; }
        public DateTime StartDate { get; set; }
        public DateTime EndDate { get; set; }
        public string Duration { get; set; }
        public int Progress { get; set; }
        public List<TaskData> SubTasks { get; set; }
    }

    public static List <TaskData> GetTaskCollection() {
    List <TaskData> Tasks = new List <TaskData> () {
        new TaskData() {
            TaskId = 1,
            TaskName = "Project initiation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 2,
                    TaskName = "Identify Site location",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 3,
                    TaskName = "Perform soil test",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "4",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 4,
                    TaskName = "Soil test approval",
                    StartDate = new DateTime(2019, 04, 02),
                    Duration = "0",
                    Progress = 30,
                },
            })
        },
        new TaskData() {
            TaskId = 5,
            TaskName = "Project estimation",
            StartDate = new DateTime(2019, 04, 02),
            EndDate = new DateTime(2019, 04, 21),
            SubTasks = (new List <TaskData> () {
                new TaskData() {
                    TaskId = 6,
                    TaskName = "Develop floor plan for estimation",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 30,
                },
                new TaskData() {
                    TaskId = 7,
                    TaskName = "List materials",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "3",
                    Progress = 40,
                },
                new TaskData() {
                    TaskId = 8,
                    TaskName = "Estimation approval",
                    StartDate = new DateTime(2019, 04, 04),
                    Duration = "0",
                    Progress = 30,
                },
            })
        }
    };

    return Tasks;
}
}