Example of Workweek in ASP.NET Core Gantt Chart Control
This sample visualizes the support for changing different set of working days in a week. The selected working days in drop down list will be applied to Gantt chart.
ID | Name | Start Date | Duration | Progress | Dependency |
---|---|---|---|---|---|
1 | Product concept | 4/2/2024 | 5 days | 18 | |
2 | Defining the product and its usage | 4/2/2024 | 3 days | 30 | |
3 | Defining target audience | 4/2/2024 | 3 days | 0 | |
4 | Prepare product sketch and notes | 4/5/2024 | 2 days | 30 | 2FS |
5 | Concept approval | 4/4/2024 | 0 days | 0 | 3FS |
6 | Market research | 4/5/2024 | 8 days | 15 | |
7 | Demand analysis | 4/5/2024 | 4 days | 15 | |
8 | Customer strength | 4/5/2024 | 4 days | 30 | 5FS |
9 | Market opportunity analysis | 4/5/2024 | 4 days | 0 | 5FS |
10 | Competitor analysis | 4/11/2024 | 4 days | 30 | 7FS |
11 | Product strength analsysis | 4/11/2024 | 4 days | 0 | 9FS |
12 | Research complete | 4/16/2024 | 0 days | 0 | 10FS |
13 | Product design and development | 4/17/2024 | 20 days | 13 | |
14 | Functionality design | 4/17/2024 | 3 days | 30 | 12FS |
15 | Quality design | 4/17/2024 | 3 days | 0 | 12FS |
16 | Define reliability | 4/22/2024 | 2 days | 30 | 15FS |
17 | Identifying raw materials | 4/22/2024 | 2 days | 0 | 15FS |
18 | Define cost plan | 4/24/2024 | 2 days | 15 | |
19 | Manufacturing cost | 4/24/2024 | 2 days | 30 | 17FS |
20 | Selling cost | 4/24/2024 | 2 days | 0 | 17FS |
21 | Development of the final design | 4/26/2024 | 7 days | 8 | |
22 | Defining dimensions and package volume | 4/26/2024 | 2 days | 30 | 19FS |
23 | Develop design to meet industry standards | 4/30/2024 | 2 days | 0 | 22FS |
24 | Include all the details | 5/2/2024 | 3 days | 0 | 23FS |
25 | CAD computer-aided design | 5/7/2024 | 3 days | 30 | 24FS |
26 | CAM computer-aided manufacturing | 5/10/2024 | 3 days | 0 | 25FS |
27 | Design complete | 5/14/2024 | 0 days | 0 | 26FS |
28 | Prototype testing | 5/15/2024 | 4 days | 30 | 27FS |
29 | Include feedback | 5/15/2024 | 4 days | 0 | 28SS |
30 | Manufacturing | 5/21/2024 | 5 days | 30 | 28FS |
31 | Assembling materials to finsihed goods | 5/28/2024 | 5 days | 0 | 30FS |
32 | Feedback and testing | 6/4/2024 | 6 days | 47 | |
33 | Internal testing and feedback | 6/4/2024 | 3 days | 45 | 31FS |
34 | Customer testing and feedback | 6/7/2024 | 3 days | 50 | 33FS |
35 | Final product development | 6/12/2024 | 4 days | 30 | |
36 | Important improvements | 6/12/2024 | 4 days | 30 | 34FS |
37 | Address any unforeseen issues | 6/12/2024 | 4 days | 30 | 36SS |
38 | Final product | 6/18/2024 | 8 days | 15 | |
39 | Branding product | 6/18/2024 | 4 days | 0 | 37FS |
40 | Marketing and presales | 6/24/2024 | 4 days | 30 | 39FS |
Mar 24, 2024 | Mar 31, 2024 | Apr 07, 2024 | Apr 14, 2024 | Apr 21, 2024 | Apr 28, 2024 | May 05, 2024 | May 12, 2024 | May 19, 2024 | May 26, 2024 | Jun 02, 2024 | Jun 09, 2024 | Jun 16, 2024 | Jun 23, 2024 | Jun 30, 2024 |
---|
S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F | S | S | M | T | W | T | F |
---|
Working Days
|
|
In this example, you can see how to render a Gantt chart with the provided data source and customizable array of working days. These working days alone will be considered for taskbar rendering and duration calculations.
The working days in your project can be customized using the workWeek property and the selected days in the dropdown list available in the property panel will be applied to Gantt chart. You can get to know the working days in the Gantt chart timeline by the highlighted weekend days. This can be enabled by using the highlightWeekends property