Example of Dependency Types in ASP.NET Core Gantt Control
The Gantt Chart supports dependency types to define relationships between tasks, helping control execution order and project sequencing.
The Gantt Chart supports various dependency relationship
types to manage task links. The
allowedDependencyTypes property is used
to restrict the dependency types available during task
editing and dependency creation.
The different dependency types are:
FS- Finish to StartSS- Start to StartFF- Finish to FinishSF- Start to Finish
When dependency types are configured, the Gantt validates newly created and modified links against the selected relationship types.
More information on the Essential® Gantt Chart can be found in this task dependency documentation section.